Shawboro Solar
BetaActiveSolarPJMLBNL + Live
150 MW generation in Currituck, NC · In queue since July 2018 · Proposed COD December 2027
150 MW
Capacity
1
Components
Solar
7y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
9y 5m
Construction75%
Queue EntryJul 31, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
NC
County
Currituck
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Shawboro-Sligo 230 kV
Data Source
LBNL + Live
No news available for this project.