Broomstick Solar Energy Centergy Center
BetaSuspendedSolarPJMLBNL + Live
50 MW generation in Christian, IL · In queue since March 2018 · Proposed COD December 2028
50 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
10y 9m
Suspended75%
Queue EntryMar 24, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-12-07
Project Details
State
IL
County
Christian
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Kincaid-Pana 345kV
Data Source
LBNL + Live
No news available for this project.