Energy Mountain — Project Summary

Queue ID
PJM-AD2-077
Capacity
150 MW
Technology
Battery
Status
suspended
Location
Bucks, PA
Region
PJM
Developer
IA Status
IA Executed

Energy Mountain

BetaSuspendedBatteryPJMLBNL + Live

150 MW storage in Bucks, PA · In queue since March 2018 · Proposed COD July 2029

150 MW

Capacity

1

Components

Battery

8 years

In Queue

IA Executed

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

11y 4m

Suspended75%
Queue EntryMar 16, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 6–18 months

Commercial Operation

Proposed COD: 2029-07-31

Project Details

State

PA

County

Bucks

Region

PJM

Developer

Utility

PPL

Entity

PJM

Point of Interconnection

Buxmont 69 kV

Data Source

LBNL + Live

No news available for this project.