Energy Mountain
BetaSuspendedBatteryPJMLBNL + Live
150 MW storage in Bucks, PA · In queue since March 2018 · Proposed COD July 2029
150 MW
Capacity
1
Components
Battery
8 years
In Queue
IA Executed
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
11y 4m
Suspended75%
Queue EntryMar 16, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 6–18 months
Commercial Operation
Proposed COD: 2029-07-31
Project Details
State
PA
County
Bucks
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Buxmont 69 kV
Data Source
LBNL + Live
No news available for this project.