Waller Solar I
BetaActiveSolarPJMLBNL + Live
86 MW generation in Lancaster, VA · In queue since March 2018 · Proposed COD December 2027
86 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
9y 9m
Construction75%
Queue EntryMar 15, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
VA
County
Lancaster
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Garner DP-Lancaster 115 kV
Data Source
LBNL + Live