Harvey Solar I
BetaActiveSolarPJMLBNL + Live
150 MW generation in Licking, OH · In queue since March 2018 · Proposed COD January 2028
150 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 10m
Construction75%
Queue EntryMar 2, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-01-15
Project Details
State
OH
County
Licking
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Centerburg 138kV
Data Source
LBNL + Live
No news available for this project.