Harvey Solar I — Project Summary

Queue ID
PJM-AD2-067
Capacity
150 MW
Technology
Solar
Status
active
Location
Licking, OH
Region
PJM
Developer
IA Status
IA Executed

Harvey Solar I

BetaActiveSolarPJMLBNL + Live

150 MW generation in Licking, OH · In queue since March 2018 · Proposed COD January 2028

150 MW

Capacity

1

Components

Solar

8 years

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

9y 10m

Construction75%
Queue EntryMar 2, 2018

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-01-15

Project Details

State

OH

County

Licking

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Centerburg 138kV

Data Source

LBNL + Live

No news available for this project.