BetaActiveSolarPJMLBNL + Live
116 MW generation in Grundy, IL · In queue since March 2018 · Proposed COD September 2026
116 MW
Capacity
1
Components
Solar
8 years
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
8y 6m
Construction75%
Queue EntryMar 1, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
IL
County
Grundy
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Mazon-Crescent Ridge 138 kV
Data Source
LBNL + Live