Staley Solar
20 MW generation in Kankakee, IL · In queue since February 2018 · Proposed COD June 2024
20 MW
Capacity
1
Components
Solar
8y 1m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
6y 4m
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-06-28
State
IL
County
Kankakee
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Davis Creek 138kV
Data Source
LBNL + Live
Ormat signs hybrid tax equity partnership with Morgan Stanley Renewables
Geothermal and renewable energy company Ormat Technologies has signed a $62m hybrid tax equity partnership with Morgan Stanley Renewables for two energy...
Morgan Stanley raised MGE Energy (MGEE) price target during utilities review
MGE Energy, Inc. (NASDAQ:MGEE) is included among the Dividend Kings List: Top 15 Stocks. On February 20, Morgan Stanley raised its price...
Morgan Stanley raised MGE Energy (MGEE) price target during utilities review
MGE Energy, Inc. (NASDAQ:MGEE) is included among the Dividend Kings List: Top 15 Stocks. On February 20, Morgan Stanley raised its price...
Morgan Stanley raised MGE Energy (MGEE) price target during utilities review
MGE Energy, Inc. (NASDAQ:MGEE) is included among the Dividend Kings List: Top 15 Stocks. On February 20, Morgan Stanley raised its price...
Last updated 2026-03-26