Blue Moon Solar
BetaActiveSolarPJMLBNL + Live
70 MW generation in Harrison, KY · In queue since February 2018 · Proposed COD December 2026
70 MW
Capacity
1
Components
Solar
8y 1m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
8y 10m
Construction75%
Queue EntryFeb 1, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
KY
County
Harrison
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Cynthia-Headquarters 69 kV
Data Source
LBNL + Live