Lower Crossing Wind
200 MW generation in Kankakee, IL · In queue since January 2018 · Proposed COD November 2026
200 MW
Capacity
1
Components
Wind
8y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
8y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–36 months
Proposed COD: 2026-11-30
State
IL
County
Kankakee
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Davis Creek 138 kV
Data Source
LBNL + Live
ComEd opens expanded Wilton Center substation in Illinois
ComEd powered up the expansion of its 765 kilovolt Wilton Center substation in southern Will County in Illinois. The substation expansion is a necessary...
ComEd opens expanded Wilton Center substation in Illinois
ComEd powered up the expansion of its 765 kilovolt Wilton Center substation in southern Will County in Illinois. The substation expansion is a necessary...
ComEd opens expanded Wilton Center substation in Illinois
ComEd powered up the expansion of its 765 kilovolt Wilton Center substation in southern Will County in Illinois. The substation expansion is a necessary...
ComEd opens expanded Wilton Center substation in Illinois
ComEd powered up the expansion of its 765 kilovolt Wilton Center substation in southern Will County in Illinois. The substation expansion is a necessary...