Osagrove Flats Wind
BetaActiveWindPJMLBNL + Live
150 MW generation in Lasalle, IL · In queue since January 2018 · Proposed COD October 2026
150 MW
Capacity
1
Components
Wind
8y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
8y 9m
Construction75%
Queue EntryJan 22, 2018
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-10-30
Project Details
State
IL
County
Lasalle
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Powerton-Nevada 345 kV
Data Source
LBNL + Live