Southwest Michigan Energy Center — Project Summary

Queue ID
PJM-AD2-020
Capacity
100 MW
Technology
Solar
Status
active
Location
Van Buren, MI
Region
PJM
Developer
IA Status
IA Executed

Southwest Michigan Energy Center

BetaActiveSolarPJMLBNL + Live

100 MW generation in Van Buren, MI · In queue since December 2017 · Proposed COD July 2028

100 MW

Capacity

1

Components

Solar

8y 3m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

10y 7m

Construction75%
Queue EntryDec 1, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-07-31

Project Details

State

MI

County

Van Buren

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Valley 138 kV

Data Source

LBNL + Live

No news available for this project.