Southwest Michigan Energy Center
BetaActiveSolarPJMLBNL + Live
100 MW generation in Van Buren, MI · In queue since December 2017 · Proposed COD July 2028
100 MW
Capacity
1
Components
Solar
8y 3m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
10y 7m
Construction75%
Queue EntryDec 1, 2017
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-07-31
Project Details
State
MI
County
Van Buren
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Valley 138 kV
Data Source
LBNL + Live
No news available for this project.