Steubenville Solar
BetaSuspendedSolarPJMLBNL + Live
49.5 MW generation in Jefferson, OH · In queue since November 2017 · Proposed COD December 2027
49.5 MW
Capacity
1
Components
Solar
8y 4m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
10y 1m
Suspended75%
Queue EntryNov 10, 2017
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
OH
County
Jefferson
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Steubenville 69 kV
Data Source
LBNL + Live
No news available for this project.