Wild Indigo Solar
BetaSuspendedSolarPJMLBNL + Live
150 MW generation in Surry, VA · In queue since October 2017 · Proposed COD September 2026
150 MW
Capacity
1
Components
Solar
8y 5m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
8y 11m
Suspended75%
Queue EntryOct 1, 2017
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
VA
County
Surry
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Hopewell-Surry 230 kV
Data Source
LBNL + Live
No news available for this project.