Short Mountain Wind Energy
BetaSuspendedWindPJMLBNL + Live
80 MW generation in Hardy, WV · In queue since September 2017 · Proposed COD December 2024
80 MW
Capacity
1
Components
Wind
8y 6m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
7y 3m
Suspended75%
Queue EntrySep 28, 2017
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–36 months
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
WV
County
Hardy
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Baker 138 kV
Data Source
LBNL + Live
No news available for this project.