Chestnut Solar
BetaActiveSolarPJMLBNL + Live
60 MW generation in Marion, OH · In queue since September 2017 · Proposed COD December 2028
60 MW
Capacity
1
Components
Solar
8y 6m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
11y 3m
Construction75%
Queue EntrySep 23, 2017
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
OH
County
Marion
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
North Waldo-Wild Creek 138 kV
Data Source
LBNL + Live
No news available for this project.