Sweet Sue Solar — Project Summary

Queue ID
PJM-AD1-105
Capacity
74 MW
Technology
Solar
Status
active
Location
King William, VA
Region
PJM
Developer
IA Status
System Impact Study

Sweet Sue Solar

BetaActiveSolarPJMLBNL + Live

74 MW generation in King William, VA · In queue since September 2017 · Proposed COD December 2026

74 MW

Capacity

1

Components

Solar

8y 6m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

9y 3m

Impact Study25%
Queue EntrySep 23, 2017

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

VA

County

King William

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Kings Dominion DP 115 kV

Data Source

LBNL + Live

No news available for this project.