— Project Summary

Queue ID
PJM-AD1-100
Capacity
850 MW
Technology
Wind
Status
active
Location
Ford, IL
Region
PJM
Developer
IA Status
IA Executed

BetaActiveWindPJMLBNL + Live

850 MW generation in Ford, IL · In queue since September 2017 · Proposed COD December 2028

850 MW

Capacity

1

Components

Wind

8y 6m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

11y 3m

Construction75%
Queue EntrySep 22, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

IL

County

Ford

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV

Data Source

LBNL + Live

No news available for this project.