Sweetleaf Solar
BetaSuspendedSolarPJMLBNL + Live
60 MW generation in Halifax, NC · In queue since August 2017 · Proposed COD January 2027
60 MW
Capacity
1
Components
Solar
8y 7m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
9y 5m
Suspended75%
Queue EntryAug 14, 2017
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-01-28
Project Details
State
NC
County
Halifax
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Hornertown-Hathaway 230 kV
Data Source
LBNL + Live
No news available for this project.