Three Rivers Energy Center
BetaActiveGasPJMLBNL + Live
102.7 MW generation in Grundy, IL · In queue since January 1970 · Proposed COD February 2025
102.7 MW
Capacity
1
Components
Gas
56y 2m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
55y 1m
Schedule
13 months past proposed COD
Construction75%
Queue EntryJan 1, 1970
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2025-02-28
Project Details
State
IL
County
Grundy
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Kendall-Tazewell & Dresden-Mole Creek
Data Source
LBNL + Live