Sumac Solar
80 MW generation in Bertie, NC · In queue since June 2017 · Proposed COD July 2028
80 MW
Capacity
1
Components
Solar
8y 9m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
11y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-07-01
State
NC
County
Bertie
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Cashie-Trowbridge 230 kV
Data Source
LBNL + Live
Local solar developer Geenex sells two North Carolina projects as part of larger deal with EDF Renewables
As part of the deal, Geenex Solar has sold two projects under development in North Carolina to EDF Renewables of San Diego.
Local solar developer Geenex sells two North Carolina projects as part of larger deal with EDF Renewables
As part of the deal, Geenex Solar has sold two projects under development in North Carolina to EDF Renewables of San Diego.
Local solar developer Geenex sells two North Carolina projects as part of larger deal with EDF Renewables
As part of the deal, Geenex Solar has sold two projects under development in North Carolina to EDF Renewables of San Diego.
Local solar developer Geenex sells two North Carolina projects as part of larger deal with EDF Renewables
As part of the deal, Geenex Solar has sold two projects under development in North Carolina to EDF Renewables of San Diego.
Last updated 2026-03-26