Sumac Solar — Project Summary

Queue ID
PJM-AD1-022
Capacity
80 MW
Technology
Solar
Status
active
Location
Bertie, NC
Region
PJM
Developer
IA Status
IA Executed

Sumac Solar

BetaActiveSolarPJMLBNL + Live

80 MW generation in Bertie, NC · In queue since June 2017 · Proposed COD July 2028

80 MW

Capacity

1

Components

Solar

8y 9m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

11y 1m

Construction75%
Queue EntryJun 19, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-07-01

Project Details

State

NC

County

Bertie

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Cashie-Trowbridge 230 kV

Data Source

LBNL + Live