Rochelle Solar — Project Summary

Queue ID
PJM-AD1-013
Capacity
40 MW
Technology
Solar
Status
active
Location
Ogle, IL
Region
PJM
Developer
IA Status
IA Executed

Rochelle Solar

BetaActiveSolarPJMLBNL + Live

40 MW generation in Ogle, IL · In queue since April 2017 · Proposed COD May 2028

40 MW

Capacity

1

Components

Solar

8y 11m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

11y 1m

Construction75%
Queue EntryApr 6, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-05-27

Project Details

State

IL

County

Ogle

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Twombly Road 138kV

Data Source

LBNL + Live

No news available for this project.