Marion County Solar Project — Project Summary

Queue ID
PJM-AC2-195
Capacity
99.96 MW
Technology
Solar
Status
active
Location
Marion, OH
Region
PJM
Developer
IA Status
IA Executed

Marion County Solar Project

BetaActiveSolarPJMLBNL + Live

99.96 MW generation in Marion, OH · In queue since April 2017 · Proposed COD December 2025

99.96 MW

Capacity

1

Components

Solar

8y 11m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

8y 8m

Schedule

3 months past proposed COD

Construction75%
Queue EntryApr 1, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

OH

County

Marion

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Galion-Roberts South 138 kV

Data Source

LBNL + Live

No news available for this project.