Raceway Solar — Project Summary

Queue ID
PJM-AC2-188
Capacity
20 MW
Technology
Solar
Status
active
Location
Kent, DE
Region
PJM
Developer
IA Status
IA Executed

Raceway Solar

BetaActiveSolarPJMLBNL + Live

20 MW generation in Kent, DE · In queue since March 2017 · Proposed COD March 2025

20 MW

Capacity

1

Components

Solar

9 years

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

8 years

Schedule

13 months past proposed COD

Construction75%
Queue EntryMar 31, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-03-01

Project Details

State

DE

County

Kent

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

Harrington 69 kV

Data Source

LBNL + Live