Raceway Solar
10 MW generation in Kent, DE · In queue since April 2017 · Proposed COD March 2025
10 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
7y 11m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-03-01
State
DE
County
Kent
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Harrington 25kV
Data Source
LBNL + Live
Bills introduced to increase utility transparency, stakeholders talk energy supply and demand issues
Lawmakers introduce a three bill package to promote more transparency within the energy sector following sharp bill increases in winter months.
Brookfield commences permitting for Oregon 4GWh hybrid BESS facility
Brookfield Renewable US has entered the permitting process for a hybrid solar and BESS facility which would be among the biggest in the world to date in terms...
Brookfield commences permitting for Oregon 4GWh hybrid BESS facility
Brookfield Renewable US has entered the permitting process for a hybrid solar and BESS facility which would be among the biggest in the world to date in terms...
Amazon inks deal for Cedar Creek solar power
Amazon made its largest investment in renewable energy yet in Delaware after signing a deal for more than of Cedar Creek Solar Farm's power.
Last updated 2026-03-26