Cedar Creek Solar — Project Summary

Queue ID
PJM-AC2-185
Capacity
20 MW
Technology
Solar
Status
suspended
Location
Kent, DE
Region
PJM
Developer
IA Status
IA Executed

Cedar Creek Solar

BetaSuspendedSolarPJMLBNL + Live

20 MW generation in Kent, DE · In queue since April 2017 · Proposed COD May 2027

20 MW

Capacity

1

Components

Solar

8y 11m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

10y 1m

Suspended75%
Queue EntryApr 1, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-05-30

Project Details

State

DE

County

Kent

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

Cedar Creek 138kV II

Data Source

LBNL + Live