Cartersville Solar
BetaSuspendedSolarPJMLBNL + Live
99.9 MW generation in Powhatan, VA · In queue since March 2017 · Proposed COD May 2026
99.9 MW
Capacity
1
Components
Solar
9 years
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
9y 2m
Suspended75%
Queue EntryMar 30, 2017
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-05-17
Project Details
State
VA
County
Powhatan
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Bremo-Powhatan 230kV
Data Source
LBNL + Live
No news available for this project.