Sycamore Cross Solar
240 MW generation in Isle Of Wight, VA · In queue since March 2017 · Proposed COD April 2026
240 MW
Capacity
1
Components
Solar
9 years
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
9y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-04-01
State
VA
County
Isle Of Wight
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Septa 500kV
Data Source
LBNL + Live
Isle of Wight approves Sycamore Cross, 11th and largest solar farm
Isle of Wight County supervisors, in separate 3-2 votes, approved the county's 11th and largest solar farm and rejected a smaller project...
Isle of Wight approves Sycamore Cross, 11th and largest solar farm
Isle of Wight County supervisors, in separate 3-2 votes, approved the county's 11th and largest solar farm and rejected a smaller project...
Sycamore Cross, IW's largest proposed solar farm, headed to Planning C...
Sycamore Cross Solar LLC, the 10th and largest proposed solar farm in Isle of Wight County, should reach the Planning Commission by spring,...
Sycamore Cross, IW's largest proposed solar farm, headed to Planning C...
Sycamore Cross Solar LLC, the 10th and largest proposed solar farm in Isle of Wight County, should reach the Planning Commission by spring,...
Last updated 2026-03-26