Firelands Wind
297.66 MW generation in Erie, OH · In queue since March 2017 · Proposed COD July 2027
297.66 MW
Capacity
1
Components
Wind
9 years
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
10y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-07-30
State
OH
County
Erie
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Beaver-Davis Besse 345 kV I
Data Source
LBNL + Live
OPSB makes decisions on multiple solar facilities
The Ohio Power Siting Board approved Clear Mountain Energy Center's solar farm in Clermont County and denied Richwood Solar's proposal in...
OPSB makes decisions on multiple solar facilities
The Ohio Power Siting Board approved Clear Mountain Energy Center's solar farm in Clermont County and denied Richwood Solar's proposal in...
OPSB Denies Rehearing for Circleville Solar Project, Approves Modifications for Several Energy Projects
Columbus, OH – January 16, 2025 – The Ohio Power Siting Board (OPSB) has denied a rehearing request filed by Circleville Solar,...
Court Approves Permit for Northwest Ohio Wind Farm
The Supreme Court of Ohio today approved the permit for construction of a 71-turbine wind farm that spans across portions of Huron and Erie counties.
Last updated 2026-03-26