Eaton OH Solar
BetaActiveSolarPJMLBNL + Live
20 MW generation in Preble, OH · In queue since February 2017 · Proposed COD January 2027
20 MW
Capacity
1
Components
Solar
9y 1m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
9y 11m
Construction75%
Queue EntryFeb 27, 2017
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-01-28
Project Details
State
OH
County
Preble
Region
PJM
Developer
—
Utility
Dayton
Entity
PJM
Point of Interconnection
Camden-Crystal II 69kV
Data Source
LBNL + Live
No news available for this project.