Porter Mill Solar
BetaSuspendedSolarPJMLBNL + Live
45.8 MW generation in Wicomico, MD · In queue since January 2017 · Proposed COD September 2026
45.8 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
9y 8m
Suspended75%
Queue EntryJan 25, 2017
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
MD
County
Wicomico
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Hebron 69kV
Data Source
LBNL + Live
No news available for this project.