Porter Mill Solar — Project Summary

Queue ID
PJM-AC2-023
Capacity
45.8 MW
Technology
Solar
Status
suspended
Location
Wicomico, MD
Region
PJM
Developer
IA Status
IA Executed

Porter Mill Solar

BetaSuspendedSolarPJMLBNL + Live

45.8 MW generation in Wicomico, MD · In queue since January 2017 · Proposed COD September 2026

45.8 MW

Capacity

1

Components

Solar

9y 2m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

9y 8m

Suspended75%
Queue EntryJan 25, 2017

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-09-30

Project Details

State

MD

County

Wicomico

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

Hebron 69kV

Data Source

LBNL + Live

No news available for this project.