80 MW generation in Hanover, VA · In queue since October 2016 · Proposed COD March 2027
80 MW
Capacity
1
Components
Solar
9y 5m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
10y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-31
State
VA
County
Hanover
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Elmont 115kV
Data Source
LBNL + Live
Springfield solar project highlights $50 million statewide initiative to cut energy costs
The Healey-Driscoll Administration announced a $50 million funding initiative aimed at reducing long-term energy costs and accelerating clean energy adoption.
Springfield solar project highlights $50 million statewide initiative to cut energy costs
The Healey-Driscoll Administration announced a $50 million funding initiative aimed at reducing long-term energy costs and accelerating clean energy adoption.
Dodge County Solar Farm to power around 25,000 homes
Alliant Energy's 100-megawatt Springfield Solar Farm in Lomira will create enough energy to power around 25000 homes according to the...
City Utilities says no new Springfield solar farm yet, due to expense
City Utilities said Thursday that it will not move forward on a proposed second solar power farm near the Springfield-Branson National Airport.
Last updated 2026-03-26