New Market Solar
BetaSuspendedSolarPJMLBNL + Live
50 MW generation in Dorchester, MD · In queue since October 2016 · Proposed COD July 2028
50 MW
Capacity
1
Components
Solar
9y 5m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
11y 9m
Suspended75%
Queue EntryOct 31, 2016
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-07-01
Project Details
State
MD
County
Dorchester
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
East New Market 69kV
Data Source
LBNL + Live