New Market Solar — Project Summary

Queue ID
PJM-AC1-190
Capacity
50 MW
Technology
Solar
Status
suspended
Location
Dorchester, MD
Region
PJM
Developer
IA Status
IA Executed

New Market Solar

BetaSuspendedSolarPJMLBNL + Live

50 MW generation in Dorchester, MD · In queue since October 2016 · Proposed COD July 2028

50 MW

Capacity

1

Components

Solar

9y 5m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

11y 9m

Suspended75%
Queue EntryOct 31, 2016

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-07-01

Project Details

State

MD

County

Dorchester

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

East New Market 69kV

Data Source

LBNL + Live