Dixon Solar — Project Summary

Queue ID
PJM-AC1-188
Capacity
70 MW
Technology
Solar
Status
active
Location
Jackson, OH
Region
PJM
Developer
IA Status
IA Executed

Dixon Solar

BetaActiveSolarPJMLBNL + Live

70 MW generation in Jackson, OH · In queue since November 2016 · Proposed COD February 2028

70 MW

Capacity

1

Components

Solar

9y 4m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

11y 3m

Construction75%
Queue EntryNov 1, 2016

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-02-28

Project Details

State

OH

County

Jackson

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Rio-Lick 138kV

Data Source

LBNL + Live

No news available for this project.