Dixon Solar
BetaActiveSolarPJMLBNL + Live
70 MW generation in Jackson, OH · In queue since November 2016 · Proposed COD February 2028
70 MW
Capacity
1
Components
Solar
9y 4m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
11y 3m
Construction75%
Queue EntryNov 1, 2016
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-02-28
Project Details
State
OH
County
Jackson
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Rio-Lick 138kV
Data Source
LBNL + Live
No news available for this project.