Mark Center Solar Project
BetaActiveSolarPJMLBNL + Live
49.9 MW generation in Defiance, OH · In queue since November 2016 · Proposed COD September 2026
49.9 MW
Capacity
1
Components
Solar
9y 4m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
9y 10m
Construction75%
Queue EntryNov 1, 2016
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
OH
County
Defiance
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Mark Center 69kV
Data Source
LBNL + Live
No news available for this project.