Cricket Solar — Project Summary

Queue ID
PJM-AC1-120
Capacity
60 MW
Technology
Solar
Status
active
Location
Culpeper, VA
Region
PJM
Developer
IA Status
IA Executed

Cricket Solar

BetaActiveSolarPJMLBNL + Live

60 MW generation in Culpeper, VA · In queue since October 2016 · Proposed COD February 2029

60 MW

Capacity

1

Components

Solar

9y 5m

In Queue

IA Executed

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

12y 4m

Construction75%
Queue EntryOct 29, 2016

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2029-02-28

Project Details

State

VA

County

Culpeper

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Mitchell-Mountain Run 115kV

Data Source

LBNL + Live

No news available for this project.