Pike County Solar
BetaActiveSolarPJMLBNL + Live
50 MW generation in Pike, KY · In queue since October 2016 · Proposed COD December 2028
50 MW
Capacity
1
Components
Solar
9y 5m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
12y 2m
Construction75%
Queue EntryOct 26, 2016
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
KY
County
Pike
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Johns Creek-Excel 138kV I
Data Source
LBNL + Live