Pike County Solar — Project Summary

Queue ID
PJM-AC1-101
Capacity
50 MW
Technology
Solar
Status
active
Location
Pike, KY
Region
PJM
Developer
IA Status
IA Executed

Pike County Solar

BetaActiveSolarPJMLBNL + Live

50 MW generation in Pike, KY · In queue since October 2016 · Proposed COD December 2028

50 MW

Capacity

1

Components

Solar

9y 5m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

12y 2m

Construction75%
Queue EntryOct 26, 2016

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

KY

County

Pike

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Johns Creek-Excel 138kV I

Data Source

LBNL + Live

No news available for this project.