Cedar Creek Solar
BetaSuspendedSolarPJMLBNL + Live
19.8 MW generation in New Castle, DE · In queue since October 2016 · Proposed COD May 2027
19.8 MW
Capacity
1
Components
Solar
9y 5m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
10y 7m
Suspended75%
Queue EntryOct 20, 2016
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-05-30
Project Details
State
DE
County
New Castle
Region
PJM
Developer
—
Utility
DPL
Entity
PJM
Point of Interconnection
Cedar Creek 138kV II
Data Source
LBNL + Live
No news available for this project.