Great Bend
48 MW generation in Meigs, OH · In queue since October 2016 · Proposed COD October 2025
48 MW
Capacity
1
Components
Solar
9y 5m
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
9 years
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-10-31
State
OH
County
Meigs
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Ravenswood-Hemlock 69kV
Data Source
LBNL + Live
Doral closes Great Bend solar financing in Ohio
Great Bend Solar project in Ohio reached final funding with tax equity, ITC transfer, and term debt from Fifth Third Bank, HSBC, and KeyBank...
Doral Renewables Completes Final Funding for Great Bend Solar Project
PRNewswire/ -- Doral Renewables, a leading, U.S. utility-scale solar and battery storage developer and independent power producer,...
Doral Renewables Completes Final Funding for Great Bend Solar Project
PR Newswire. PHILADELPHIA, March 19, 2026. PHILADELPHIA, March 19, 2026 /PRNewswire/ -- Doral Renewables, a leading, U.S. utility-scale solar and battery...
Doral Renewables Completes Final Funding for Great Bend Solar Project
PR Newswire. PHILADELPHIA, March 19, 2026. PHILADELPHIA, March 19, 2026 /PRNewswire/ -- Doral Renewables, a leading, U.S. utility-scale solar and battery...