Laurel Mountain Wind Farm & Energy Storage Facility
BetaActiveWindBatteryPJMLBNL + Live
16.3 MW hybrid in Barbour, WV · In queue since January 1970 · Proposed COD December 2019
16.3 MW
Capacity
1
Components
Wind
56y 2m
In Queue
IA Executed
IA Status
COD target: 2019
Interconnection Timeline
Total Duration
49y 11m
Schedule
76 months past proposed COD
Construction75%
Queue EntryJan 1, 1970
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–36 months
Commercial Operation
Proposed COD: 2019-12-31
Project Details
State
WV
County
Barbour
Region
PJM
Developer
—
Utility
APS
Entity
PJM
Point of Interconnection
Laurel Mountain 138 kV
Data Source
LBNL + Live
No news available for this project.