Walnut Solar I
BetaActiveSolarPJMLBNL + Live
50 MW generation in King And Queen, VA · In queue since September 2016 · Proposed COD July 2026
50 MW
Capacity
1
Components
Solar
9y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
9y 10m
Construction75%
Queue EntrySep 22, 2016
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-07-14
Project Details
State
VA
County
King And Queen
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Harmony Village-Shackleford 115kV
Data Source
LBNL + Live