Edgecome Solar Energy Center
BetaActiveSolarPJMLBNL + Live
75 MW generation in Edgecombe, NC · In queue since August 2016 · Proposed COD December 2025
75 MW
Capacity
1
Components
Solar
9y 7m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
9y 4m
Schedule
3 months past proposed COD
Construction75%
Queue EntryAug 11, 2016
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
NC
County
Edgecombe
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Heartsease DP - Mayo Dunbar 115kV
Data Source
LBNL + Live
No news available for this project.