National Park NJ — Project Summary

Queue ID
PJM-AC1-010
Capacity
6 MW
Technology
Solar
Status
active
Location
Gloucester, NJ
Region
PJM
Developer
IA Status
IA Executed

National Park NJ

BetaActiveSolarPJMLBNL + Live

6 MW generation in Gloucester, NJ · In queue since June 2016 · Proposed COD March 2026

6 MW

Capacity

1

Components

Solar

9y 9m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

9y 9m

Construction75%
Queue EntryJun 22, 2016

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-03-31

Project Details

State

NJ

County

Gloucester

Region

PJM

Developer

Utility

PSEG

Entity

PJM

Point of Interconnection

Gloucester 26kV

Data Source

LBNL + Live

No news available for this project.