National Park NJ
BetaActiveSolarPJMLBNL + Live
6 MW generation in Gloucester, NJ · In queue since June 2016 · Proposed COD March 2026
6 MW
Capacity
1
Components
Solar
9y 9m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
9y 9m
Construction75%
Queue EntryJun 22, 2016
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
NJ
County
Gloucester
Region
PJM
Developer
—
Utility
PSEG
Entity
PJM
Point of Interconnection
Gloucester 26kV
Data Source
LBNL + Live