Morgnec Road Solar — Project Summary

Queue ID
PJM-AB2-133
Capacity
55.8 MW
Technology
Solar
Status
active
Location
Kent, MD
Region
PJM
Developer
IA Status
IA Executed

Morgnec Road Solar

BetaActiveSolarPJMLBNL + Live

55.8 MW generation in Kent, MD · In queue since April 2016 · Proposed COD July 2026

55.8 MW

Capacity

1

Components

Solar

9y 11m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

10y 3m

Construction75%
Queue EntryApr 29, 2016

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-07-31

Project Details

State

MD

County

Kent

Region

PJM

Developer

Utility

DPL

Entity

PJM

Point of Interconnection

Chestertown-Church 69kV

Data Source

LBNL + Live

No news available for this project.