— Project Summary

Queue ID
PGE-24-258
Capacity
225 MW
Technology
Solar+Battery
Status
active
Location
Jefferson, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPGELBNL

225 MW hybrid in Jefferson, OR · In queue since May 2024 · Proposed COD July 2028

225 MW

Capacity

1

Components

Solar

1y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 2m

In Study38%
Queue EntryMay 24, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-31

Project Details

State

OR

County

Jefferson

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Round Butte 230kV Substation

Data Source

LBNL

No news available for this project.