— Project Summary

Queue ID
PGE-24-247
Capacity
200 MW
Technology
Battery
Status
active
Location
Columbia, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPGELBNL

200 MW storage in Columbia, OR · In queue since May 2024 · Proposed COD June 2027

200 MW

Capacity

1

Components

Battery

1y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 1m

In Study38%
Queue EntryMay 20, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

OR

County

Columbia

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Kaster Substation 115 kV

Data Source

LBNL

No news available for this project.