— Project Summary

Queue ID
PGE-24-244
Capacity
65 MW
Technology
Battery
Status
active
Location
Washington, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPGELBNL

65 MW storage in Washington, OR · In queue since May 2024 · Proposed COD June 2027

65 MW

Capacity

1

Components

Battery

1y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 1m

In Study38%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-30

Project Details

State

OR

County

Washington

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Cornelius-Gales 57 kV

Data Source

LBNL