20 MW storage in Multnomah, OR · In queue since April 2024 · Proposed COD December 2027
20 MW
Capacity
1
Components
Battery
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
In Study38%
Queue EntryApr 30, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-30
Project Details
State
OR
County
Multnomah
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Hemlock Substation 115 kV
Data Source
LBNL