— Project Summary

Queue ID
PGE-24-242
Capacity
50 MW
Technology
Battery
Status
active
Location
Polk, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPGELBNL

50 MW storage in Polk, OR · In queue since April 2024 · Proposed COD December 2028

50 MW

Capacity

1

Components

Battery

1y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 8m

In Study38%
Queue EntryApr 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

OR

County

Polk

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Willamina Substation 57 kV

Data Source

LBNL

No news available for this project.