BetaActiveBatteryPGELBNL
50 MW storage in Polk, OR · In queue since April 2024 · Proposed COD December 2028
50 MW
Capacity
1
Components
Battery
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 8m
In Study38%
Queue EntryApr 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
OR
County
Polk
Region
West
Developer
—
Utility
Portland General Electric
Entity
PGE
Point of Interconnection
Willamina Substation 57 kV
Data Source
LBNL