— Project Summary

Queue ID
PGE-24-240
Capacity
130 MW
Technology
Solar+Battery
Status
active
Location
Jefferson, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryPGELBNL

130 MW hybrid in Jefferson, OR · In queue since January 2024 · Proposed COD October 2027

130 MW

Capacity

1

Components

Solar

2y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 9m

In Study38%
Queue EntryJan 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-23

Project Details

State

OR

County

Jefferson

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Redmond - Round Butte 230kV

Data Source

LBNL