— Project Summary

Queue ID
PGE-23-239
Capacity
200 MW
Technology
Battery
Status
active
Location
Multnomah, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryPGELBNL

200 MW storage in Multnomah, OR · In queue since December 2023 · Proposed COD December 2028

200 MW

Capacity

1

Components

Battery

2y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5 years

In Study38%
Queue EntryDec 15, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

OR

County

Multnomah

Region

West

Developer

Utility

Portland General Electric

Entity

PGE

Point of Interconnection

Rivergate Substation 230kV

Data Source

LBNL